Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 on Contract 02-14 (K4-002), HVAC Renovations - Street Maintenance Garage, Southport Heating Plumbing Geothermal, contractor. (Res No. 15-0067)
Recommendation of the Public Works and Services Committee on February 10, 2015: That Change Order No. 2 on Contract 02-14 (K4-002), HVAC Renovations - Street Maintenance Garage, Southport Heating Plumbing Geothermal, contractor, as submitted, be approved in the amount of $3,228.
Further recommends that funding to defray the cost of this change order be appropriated from Account 994.410.5010 (Org-Object 45040-57200, DPW Building Improvements).