Ricine Banner
File #: 08-1750    Version: A Name: Rescind Resolution No. 08-0625 and to authorize final payment on Contract 46-07 (K7-054), Festival Hall Boiler Replacement, Mechanical Associates of WI, Inc., contractor.
Type: Communication Status: Passed
File created: 2/18/2008 In control: Public Works and Services Committee
On agenda: Final action: 3/4/2008
Title: Subject: Communication from the Commissioner of Public Works/City Engineer requesting to rescind Resolution No. 08-0625, of February 5, 2008, and to authorize final payment on Contract 46-07 (K7-054), Festival Hall Boiler Replacement, Mechanical Associates of WI, Inc., contractor. Recommendation: As the amount listed in Resolution No. 08-0625, dated February 5, 2008, was incorrect, Resolution No. 08-0625 be rescinded. Further recommends that the work of Mechanical Associates of WI, Inc., under Contract 46-07 (K7-054), Festival Hall Boiler Replacement, be accepted and final payment authorized for a total contract amount of $76,987.00, from funds heretofore appropriated. Fiscal Note: Contract was approved by Resolution 07-0358, dated August 6, 2007.
Attachments: 1. 46-07 FPR.pdf
Related files: 07-1423, Res.08-0625, Res.08-0673
Title
Subject: Communication from the Commissioner of Public Works/City Engineer requesting to rescind Resolution No. 08-0625, of February 5, 2008, and to authorize final payment on Contract 46-07 (K7-054), Festival Hall Boiler Replacement, Mechanical Associates of WI, Inc., contractor.
 
Recommendation: As the amount listed in Resolution No. 08-0625, dated February 5, 2008, was incorrect, Resolution No. 08-0625 be rescinded.
 
Further recommends that the work of Mechanical Associates of WI, Inc., under Contract 46-07 (K7-054), Festival Hall Boiler Replacement, be accepted and final payment authorized for a total contract amount of $76,987.00, from funds heretofore appropriated.
 
Fiscal Note: Contract was approved by Resolution 07-0358, dated August 6, 2007.