Ricine Banner
File #: Res.09-1329    Version: A Name: Final - Ten (10) Year Benefits & Damages
Type: Resolution Status: Passed
File created: 4/8/2009 In control: Public Works and Services Committee
On agenda: Final action: 5/6/2009
Title: Final - Ten (10) Year Benefits & Damages WHEREAS, the Public Works & Services Committee of the Common Council of the City of Racine, Wisconsin, held a public hearing at the Council Chambers in the City Hall at 5:30 P.M. on the 31st day of March, 2009, for the purpose of hearing all interested persons concerning the preliminary resolution and report of the Commissioner of Public Works on the proposed improvement of: PORTLAND CEMENT CONCRETE PAVING St. Patrick Street from Summit Avenue to the dead end. Harmony Drive from Douglas Avenue to +/-184’ east of Douglas Avenue. Fourth Avenue from South Street to Shoreland Drive. Alley - Prospect Street/Harriet Street; Booker Street/State Street. SEWER AND WATER LATERALS Harmony Drive from Douglas Avenue to +/-184’ east of Douglas Avenue Fourth Avenue from South Street to Shoreland Drive SANITARY SEWER Harmony Drive from Douglas Avenue to =/- 184’ east of Douglas Avenue CURB AND GUTTER St. Patrick Street from S...
Sponsors: Gregory Helding
Related files: 09-3426
Sponsor
Alderman Helding

Title
Final - Ten (10) Year
Benefits & Damages

WHEREAS, the Public Works & Services Committee of the Common Council of the City of Racine, Wisconsin, held a public hearing at the Council Chambers in the City Hall at 5:30 P.M. on the 31st day of March, 2009, for the purpose of hearing all interested persons concerning the preliminary resolution and report of the Commissioner of Public Works on the proposed improvement of:

PORTLAND CEMENT CONCRETE PAVING

St. Patrick Street from Summit Avenue to the dead end.
Harmony Drive from Douglas Avenue to +/-184’ east of Douglas Avenue.
Fourth Avenue from South Street to Shoreland Drive.
Alley - Prospect Street/Harriet Street; Booker Street/State Street.

SEWER AND WATER LATERALS

Harmony Drive from Douglas Avenue to +/-184’ east of Douglas Avenue
Fourth Avenue from South Street to Shoreland Drive

SANITARY SEWER

Harmony Drive from Douglas Avenue to =/- 184’ east of Douglas Avenue

CURB AND GUTTER

St. Patrick Street from Summit Avenue to the dead end.

NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Racine as follows:

1. That the report of the Commissioner of Public Works pertaining to the construction of the above described public improvements, including plans and specifications therefore, as modified, is hereby adopted and approved.

2. That the Commissioner of Public Works is directed to advertise for bids and to carry out the work of such improvement in accordance with the report of the Commissioner of Public Works.

3. That payment for said improvements be made by assessing the cost to the property benefited as indicated in said report.

4. That benefits and damages shown on the report, as modified, are true and correct, have been determined on a reasonable basis; do not exceed the value accruing to the property therefrom; and are hereby confirmed.

5. That the assessments for all projects included in said report are hereby combin...

Click here for full text