File #: 08-2773    Version: A Name: Rescind Res. 08-0850 and create a new resolution for Change Order No. 3 to Contract 10-07 (K7-010), Gaslight Drive Renovations, Cornerstone Pavers, contractor.
Type: Communication Status: Passed
File created: 10/7/2008 In control: Public Works and Services Committee
On agenda: Final action: 10/21/2008
Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering requesting to rescind Resolution 08-0850 and create a new resolution for Change Order No. 3 to Contract 10-07 (K7-010), Gaslight Drive Renovations, Cornerstone Pavers, contractor. (Res.08-1052) Recommendation of the Public Works and Services Committee on 10-14-08: That Resolution 08-0850, dated June 3, 2008, be rescinded. Further recommends that Change Order No. 3 to Contract 10-07 (K7-010), Gaslight Drive Renovations, Cornerstone Pavers, contractor, be approved in the amount of $2,226.58. Further recommends that funding to defray the cost of this change order be appropriated from Account 986.908.5010, Miscellaneous Concrete Paving. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. Ald Helding - Rescind Resolution 10-07
Related files: Res.08-1052
Title
Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering requesting to rescind Resolution 08-0850 and create a new resolution for Change Order No. 3 to Contract 10-07 (K7-010), Gaslight Drive Renovations, Cornerstone Pavers, contractor.  (Res.08-1052)
 
Recommendation of the Public Works and Services Committee on 10-14-08: That Resolution 08-0850, dated June 3, 2008, be rescinded.
 
Further recommends that Change Order No. 3 to Contract 10-07 (K7-010), Gaslight Drive Renovations, Cornerstone Pavers, contractor, be approved in the amount of $2,226.58.
 
Further recommends that funding to defray the cost of this change order be appropriated from Account 986.908.5010, Miscellaneous Concrete Paving.
 