File #: 12-8002    Version: A Name: Change Order No. 1 to Contract 1-12 (K2-001), 2012 Parking Ramp Maintenance (R1), Truesdell Corporation of WI, contractor. (RES. No. 12-3310)
Type: Communication Status: Passed
File created: 8/1/2012 In control: Public Works and Services Committee
On agenda: Final action: 9/4/2012
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 1 to Contract 1-12 (K2-001), 2012 Parking Ramp Maintenance (R1), Truesdell Corporation of WI, contractor. (RES. No. 12-3310) Recommendation of the Public Works and Services Committee on 8-14-12: Defer Recommendation of the Public Works and Services Committee on 8-28-12: That Change Order No. 1 to Contract 1-12 (K2-001), 2012 Parking Ramp Maintenance (R1), Truesdell Corporation of WI, contractor, as submitted, be approved in the deduct amount of $209,599.70. Fiscal Note: Change Order No. 1 will result in a decrease in contract price. Funding account to be adjusted is 106.992.5760, Parking - 2012 Building Improvements.
Attachments: 1. 1-12 CO #1.pdf
Related files: Res.12-3310
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 1 to Contract 1-12 (K2-001), 2012 Parking Ramp Maintenance (R1), Truesdell Corporation of WI, contractor.  (RES. No. 12-3310)
 
Recommendation of the Public Works and Services Committee on 8-14-12: Defer
 
Recommendation of the Public Works and Services Committee on 8-28-12: That Change Order No. 1 to Contract 1-12 (K2-001), 2012 Parking Ramp Maintenance (R1), Truesdell Corporation of WI, contractor, as submitted, be approved in the deduct amount of $209,599.70.
 
Fiscal Note: Change Order No. 1 will result in a decrease in contract price. Funding account to be adjusted is 106.992.5760, Parking - 2012 Building Improvements.