Ricine Banner
File #: 0332-19    Version: A Name: Change Order No. 1 on Contract 20180021, 2018 Assessable Streets and Alley Paving, Cornerstone Pavers, LLC, contractor.
Type: Communication Status: Passed
File created: 3/22/2019 In control: Public Works and Services Committee
On agenda: Final action: 4/15/2019
Title: Subject: (Direct Referral) Change Order No. 1 on Contract 20180021, 2018 Assessable Streets and Alley Paving, Cornerstone Pavers, LLC, contractor. Recommendation of the Public Works and Services Committee on 04-09-19: That Change Order No. 1 on Contract 20180021, 2018 Assessable Streets and Alley Paving, Cornerstone Pavers, LLC, contractor, be approved in the amount of $47,763.18. Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 45040-57500, Concrete Street Paving, Misc. Locations. Fiscal Note: Funds are available as herein delineated.
Sponsors: John Tate II
Attachments: 1. 0332-19 CO1 Contract 20180021, 2018 Assessable Streets and Alley Paving.pdf, 2. #0332-19 Resolution

Title

Subject: (Direct Referral) Change Order No. 1 on Contract 20180021, 2018 Assessable Streets and Alley Paving, Cornerstone Pavers, LLC, contractor.

 

Recommendation of the Public Works and Services Committee on 04-09-19: That Change Order No. 1 on Contract 20180021, 2018 Assessable Streets and Alley Paving, Cornerstone Pavers, LLC, contractor, be approved in the amount of $47,763.18.

 

Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 45040-57500, Concrete Street Paving, Misc. Locations.

 

Fiscal Note:  Funds are available as herein delineated.