Title: Change Order No. 2 on Contract 53-08 (K8-061), City Hall Renovations-Phase II (R1), Absolute Construction Enterprises, Inc., be approved Resolved, that Change Order No. 2 on Contract 53-08 (K8-061), City Hall Renovations-Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $10,721.00. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $ 1,429.00 - Account 987.100.5030, IS Renovations $ 9,292.00 - Account 989.100.5010, City Hall-Facilities Plan Implementation $10,721.00 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 09-3148
Sponsor
Alderman Helding
 
Title
Change Order No. 2 on Contract 53-08 (K8-061), City Hall Renovations-Phase II (R1), Absolute Construction Enterprises, Inc., be approved
 
Resolved, that Change Order No. 2 on Contract 53-08 (K8-061), City Hall Renovations-Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $10,721.00.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$  1,429.00 - Account 987.100.5030, IS Renovations
$  9,292.00 - Account 989.100.5010, City Hall-Facilities Plan Implementation
$10,721.00 - Total
 