Ricine Banner
File #: Res.09-1640    Version: A Name: Approval of Change Order No. 1 to Contract 23-09 (K9-024), Basin 17 & 18 Sewer Improvements, Woodland Hills Contractors
Type: Resolution Status: Passed
File created: 10/6/2009 In control: City Attorney's Office
On agenda: Final action: 10/6/2009
Title: Approval of Change Order No. 1 to Contract 23-09 (K9-024), Basin 17 & 18 Sewer Improvements, Woodland Hills Contractors Resolved, that Change Order No. 1 on Contract 23-09 (K9-024), Basin 17 & 18 Sewer Improvements, Woodland Hills Contractors, contractor, as submitted, be approved in the deduct amount of $10,993.35. Fiscal Note: Change Order No. 1 will result in a decrease in contract price.
Sponsors: Gregory Helding
Related files: 09-4003
Sponsor
Alderman Helding
 
Title
Approval of Change Order No. 1 to Contract 23-09 (K9-024), Basin 17 & 18 Sewer Improvements, Woodland Hills Contractors
 
Resolved, that Change Order No. 1 on Contract 23-09 (K9-024), Basin 17 & 18 Sewer Improvements, Woodland Hills Contractors, contractor, as submitted, be approved in the deduct amount of $10,993.35.
 
Fiscal Note:  Change Order No. 1 will result in a decrease in contract price.