Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 4 on Contract 53-08 (K8-061), City Hall Renovation - Phase II, Absolute Construction Enterprises, Inc., contractor. (Res.09-1396) Recommendation of the Public Works and Services Committee on 4-28-09: That Change Order No. 4 on Contract 53-08 (K8-061), City Hall Renovation - Phase II, Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $12,967.00. Further recommends that funding to defray the cost of this change order be appropriated from Account 988.100.5010, City Hall-Facilities Plan. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 53-08 CO #4.pdf, 2. 53-08 CO #4 to PWSC.pdf
Related files: Res.09-1396
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 4 on Contract 53-08 (K8-061), City Hall Renovation - Phase II, Absolute Construction Enterprises, Inc., contractor.  (Res.09-1396)
 
Recommendation of the Public Works and Services Committee on 4-28-09: That Change Order No. 4 on Contract 53-08 (K8-061), City Hall Renovation - Phase II, Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $12,967.00.
 
Further recommends that funding to defray the cost of this change order be appropriated from Account 988.100.5010, City Hall-Facilities Plan.
 