Ricine Banner
File #: 13-8934    Version: A Name: Final payment on Contract 48-12 (K2-059), Central Heating Plant-Boiler Upgrade, Butters-Fetting Co., Inc., contractor. (Res. No. 13-0229)
Type: Communication Status: Passed
File created: 5/6/2013 In control: Public Works and Services Committee
On agenda: Final action: 5/21/2013
Title: Subject: (Direct Referral) Communication from the Commissioner of Public Works submitting a request for final payment on Contract 48-12 (K2-059), Central Heating Plant-Boiler Upgrade, Butters-Fetting Co., Inc., contractor.(Res. No. 13-0229) Recommendation of the Public Works and Services Committee on 5-14-13: That the work done by Butters-Fetting Co., Inc. under Contract 48-12 (K2-059), Central Heating Plant Boiler Upgrade, be accepted and final payment authorized for a total contract amount of $156,150.00. Fiscal Note: Contract was authorized under Resolution No. 12-3229, dated July 17, 2012.
Attachments: 1. 48-12 Final Payment.pdf
Related files: Res.13-0229
Title
Subject: (Direct Referral) Communication from the Commissioner of Public Works submitting a request for final payment on Contract 48-12 (K2-059), Central Heating Plant-Boiler Upgrade, Butters-Fetting Co., Inc., contractor.(Res. No. 13-0229)
 
Recommendation of the Public Works and Services Committee on 5-14-13: That the work done by Butters-Fetting Co., Inc. under Contract 48-12 (K2-059), Central Heating Plant Boiler Upgrade, be accepted and final payment authorized for a total contract amount of $156,150.00.
 
Fiscal Note: Contract was authorized under Resolution No. 12-3229, dated July 17, 2012.