Title:
|
Subject: Change Order No. 2 on Contract W-24-1, 2024 Lead Service Replacements - Phase 2, Miller Pipeline, LLC (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in an overall increase of $3,057.85, bringing the contract total to $1,002,635.13.
|