File #: 0737-25    Version: A Name: Subject: Consideration of Change Order No. 2 on Contract W-25-3, 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading (contractor) Staff Recommendation: To Approve Fiscal Note: Contract Change results in an increase of $10,155.25, b
Type: Communication Status: Passed
File created: 7/12/2025 In control: Waterworks Commission
On agenda: Final action: 7/16/2025
Title: Subject: Consideration of Change Order No. 2 on Contract W-25-3, 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading (contractor) Staff Recommendation: To Approve Fiscal Note: Contract Change results in an increase of $10,155.25, bringing the total contract amount to $1,265,608.25.
Attachments: 1. w-25-3_co#2_ltr to commsrs

Title

Subject: Consideration of Change Order No. 2 on Contract W-25-3, 2025 Water Main Replacement - Phase 2, Reesman's Excavating & Grading (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract Change results in an increase of $10,155.25, bringing the total contract amount to $1,265,608.25.