Subject: (Direct Referral) Communication from the Director of Parks, Recreation and Cultural Services requesting permission to present the bids received by the Commissioner of Public Works, on September 8, 2011, for Contract No. 31-11 (K1-033), Sam Johnson Parkway Fountain Upgrades (R1). (Resolution No. 11-2740)
Recommendation of the Public Works and Services Committee on 9-13-11: That Contract 31-11 (K1-033), Sam Johnson Parkway Fountain Upgrades (R1), be awarded to Scherrer Construction Company, Burlington, WI, at their base bid price of $677,599.00, plus Alternate Bid #2 in the deduct amount of $2,400.00, for a total contract amount of $675,199.00, they being the lowest responsible bidder.
Fiscal Note: Funding to defray the cost of this public works project be appropriated from the following accounts:
$100,000.00 - Account 991.700.5040, Renovate Boat Ramp Restrooms
$575,199.00 - S.C. Johnson Donation