Subject: Communication sponsored by Alder Jones, on behalf of the Department of Public Works, to submit final payment for Contract 20200027- 2020 Sanitary and Storm Sewer CIPP Lining, Musson Brothers, Inc., Contractors.
Staff Recommendation to the Public Works and Services Committee on 05-10-22: That the work completed by Musson Brothers Inc., on Contract 20200027, 2020 Sanitary and Storm Sewer CIPP Lining, be accepted and final payment authorized for a total contract of $454,725.93. Final Payment to include retainage.