File #: 06-2730    Version: A Name: Change Order No. 3 on Contract 07-06(K6-007), 2006 CCTV Services and Manhole Inspections, Green Bay Pipe & TV, Inc., contractor.
Type: Communication Status: Passed
File created: 10/23/2006 In control: Public Works and Services Committee
On agenda: Final action: 11/8/2006
Title: Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 3 on Contract 07-06 (K6-007), 2006 CCTV Services and Manhole Inspections, Green Bay Pipe & TV, Inc., contractor. Recommendation: Change Order No. 3 on Contract 7-06 (K6-007), 2006 CCTV Services and Manhole Inspection, Green Bay Pipe & TV, contractor, as submitted, be approved in the amount of $52,174.14. Further recommends that funding to defray the cost of this change order be appropriated from the following accounts: $24,727.30 - Account 986.907.5310, Sanitary Sewer, Various Locations $27,446.84 - Account 104.986.5420, Storm Sewers, Various Locations $52,174.14 Fiscal Note: Funds are available as herein delineated.
Attachments: 1. CO #3-07-06, 2. Ald Hart - CO 3-07-06
Related files: Res.06-7299
Title
Subject:  Direct Referral.  Communication from the Assistant Commissioner of Public Works/Engineering submitting Change Order No. 3 on Contract 07-06 (K6-007), 2006 CCTV Services and Manhole Inspections, Green Bay Pipe & TV, Inc., contractor.
 
Recommendation: Change Order No. 3 on Contract 7-06 (K6-007), 2006 CCTV Services and Manhole Inspection, Green Bay Pipe & TV, contractor, as submitted, be approved in the amount of $52,174.14.
 
Further recommends that funding to defray the cost of this change order be appropriated from the following accounts:
 
$24,727.30 - Account 986.907.5310, Sanitary Sewer, Various Locations
$27,446.84 - Account 104.986.5420, Storm Sewers, Various Locations
$52,174.14
 
Fiscal Note: Funds are available as herein delineated.