Title:
|
Permission for Commissioner of Public Works to enter into a grant agreement with Focus on Energy for Phase II of the Solid Waste Garage LED Light Fixture Project
Resolved, that the Commissioner of Public Works/City Engineer be authorized and directed to enter into a grant agreement, on behalf of the City of Racine, with Focus on Energy which will provide an estimated $1,090.00 in funding for Phase II of the Solid Waste Garage LED Light Fixture project. The total estimated cost of this project is $6,700.00.
Further resolved, that funds for this project are available in Account 401.000.5670, Building Repairs and Maintenance.
Fiscal Note: The grant and resulting reduction in annual energy costs will result in less than a 4 year payback.
|