File #: Res.10-2074    Version: A Name: Contract 32-10 (K0-040), Storm and Sanitary Sewer Relining, be awarded to Musson Brothers, Inc.
Type: Resolution Status: Passed
File created: 6/15/2010 In control: City Attorney's Office
On agenda: Final action: 6/15/2010
Title: Contract 32-10 (K0-040), Storm and Sanitary Sewer Relining, be awarded to Musson Brothers, Inc. Resolved, that Contract 32-10 (K0-040), Storm and Sanitary Sewer Relining, be awarded to Musson Brothers, Inc., Rhinelander, WI, at its bid price of $390,172.85, it being the only responsible bidder. Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts: $ 93,202.85 - Account 287.988.5310, Sanitary Sewer, Misc. Loc. $ 57,000.00 - Account 287.989.5310, Sanitary Sewer, Var. Loc. $230,000.00 - Account 287.990.5310, Sanitary Sewer, Var. Loc. $ 9,970.00 - Account 104.990.5420, 10th St.Sewer Project $390,172.85 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 10-5128
Sponsor
Alderman Helding
 
Title
Contract 32-10 (K0-040), Storm and Sanitary Sewer Relining, be awarded to Musson Brothers, Inc.
 
Resolved, that Contract 32-10 (K0-040), Storm and Sanitary Sewer Relining, be awarded to Musson Brothers, Inc., Rhinelander, WI, at its bid price of $390,172.85, it being the only responsible bidder.
 
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
 
$  93,202.85 - Account 287.988.5310, Sanitary Sewer, Misc. Loc.
$  57,000.00 - Account 287.989.5310, Sanitary Sewer, Var. Loc.
$230,000.00 - Account 287.990.5310, Sanitary Sewer, Var. Loc.
$    9,970.00 - Account 104.990.5420, 10th St.Sewer Project
$390,172.85 - Total
 
Fiscal Note: Funds are available as herein delineated.