Title:
|
Subject: Communication sponsored by Alder Jones, on behalf of the Department of Public Works, to submit final payment for Contract 2021073 - Transit Center Rehabilitation Phase I (C.D.B.G), Berglund Construction Company, Contractors.
Staff Recommendation to the Public Works and Services Committee on 04-26-22: That the work completed by Berglund Construction Company, on Contract 2021073, Transit Center Rehabilitation Phase I (C.D.B.G) be accepted and final payment authorized for a total contract of $268,541.40. Final Payment to exclude retainage.
Fiscal Note: Contract 2021073 was authorized under Resolution No.0673-21, dated August 19, 2021.
|