File #: Res.06-6505    Version: A Name: CHANGE ORDER FOR RAILROAD DEPOT RESTORATION
Type: Resolution Status: Passed
File created: 1/16/2006 In control: City Attorney's Office
On agenda: 1/17/2006 Final action: 1/17/2006
Title: CHANGE ORDER FOR RAILROAD DEPOT RESTORATION

Sponsor

Alderman Engel

 

Title

CHANGE ORDER FOR RAILROAD DEPOT RESTORATION

 

Body

RESOLVED, that Change Order No. 2 on Contract 25-04 (K4-035), Racine Railroad Depot Restoration, Tri-North Builders, Inc., contractor, as submitted, be approved in the amount of $59,623.30.

 

FURTHER RESOLVED, that funding to defray the cost of this change order be appropriated from Account 105.900.5010, Capital Projects.

 

 

 

Fiscal Note