Ricine Banner
File #: Res.09-1315    Version: A Name: Contract for 2009 CCTV Service and Manhole Inspection be awarded to Green Bay Pipe & TV LLC
Type: Resolution Status: Passed
File created: 4/8/2009 In control: City Attorney's Office
On agenda: Final action: 4/8/2009
Title: Contract for 2009 CCTV Service and Manhole Inspection be awarded to Green Bay Pipe & TV LLC Resolved, that Contract 19-09 (K9-020), 2009 CCTV Service and Manhole Inspection, be awarded to Green Bay Pipe & TV, LLC, Green Bay, WI, at its bid price of $317,235.58, it being the lowest responsible bidder. Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts: $120,041.68 - Account 287.988.5310, Sanitary Sewer-Var. Loc. $197,193.90 - Account 104.900.5420, Storm Sewers, Misc. Loc. $317,235.58 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 09-3373
Sponsor
Alderman Helding
 
Title
Contract for 2009 CCTV Service and Manhole Inspection be awarded to Green Bay Pipe & TV LLC
 
Resolved, that Contract 19-09 (K9-020), 2009 CCTV Service and Manhole Inspection, be awarded to Green Bay Pipe & TV, LLC, Green Bay, WI, at its bid price of $317,235.58, it being the lowest responsible bidder.
 
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
 
$120,041.68 - Account 287.988.5310, Sanitary Sewer-Var. Loc.
$197,193.90 - Account 104.900.5420, Storm Sewers, Misc. Loc.
$317,235.58 - Total
 
Fiscal Note: Funds are available as herein delineated.