Sponsor
Alderman Weidner
Title
Change Order No. 1 on Contract 02-12 (K2-002) - 2012 Sidewalk Replacement, Phase I, AZAR LLC, Contractor
Resolved, that Change Order No. 1 on Contract 2-12 (K2-002), 2012 Sidewalk Replacement, Phase I (R1), AZAR LLC, contractor, is approved in the amount of $5,788.75.
Fiscal Note: Funding to defray the cost of this change order be appropriated from Account 906.000.5520, Sidewalk Replacement.