File #: 09-3852    Version: A Name: Change Order No. 6 on Contract 53-08 (K8-061), City Hall Renovations-Phase II (R1), Absolute Construction Enterprises, Inc.
Type: Communication Status: Passed
File created: 7/2/2009 In control: Public Works and Services Committee
On agenda: Final action: 8/3/2009
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 6 on Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc. (Res.09-1539) Recommendation of the Public Works and Services Committee on 7-28-09: That Change Order No. 6 on Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $30,943.00. Further recommends that funding to defray the cost of this change order be appropriated from Account 988.100.5010, City Hall-Facilities Plan Implementation. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 53-08 CO #6 to PWSC.pdf
Related files: Res.09-1539
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 6 on Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc.  (Res.09-1539)
 
Recommendation of the Public Works and Services Committee on 7-28-09: That Change Order No. 6 on Contract 53-08 (K8-061), City Hall Renovations, Phase II (R1), Absolute Construction Enterprises, Inc., contractor, be approved in the amount of $30,943.00.
 
Further recommends that funding to defray the cost of this change order be appropriated from Account 988.100.5010, City Hall-Facilities Plan Implementation.
 