Title:
|
Subject: Direct Referral. Communication from the Assistant Commissioner of Public Works/Engineering, submitting Change Order No. 5 on Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor.
Recommendation: That Change Order No. 5 to Contract 49-05 (K5-056), Lake Michigan Pathway, Phase II, Bane-Nelson, Inc., contractor, as submitted, be approved in the amount of $416.70.
Further recommends that funding to defray the cost of this change order be appropriated from Account 987.908.5130, Asphalt Resurfacing.
Fiscal Note: Funds are available as herein delineated.
|