Ricine Banner
File #: 10-5222    Version: A Name: Change Order No. 2 to Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor.
Type: Communication Status: Passed
File created: 6/2/2010 In control: Public Works and Services Committee
On agenda: Final action: 6/15/2010
Title: Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 to Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor. (Res.10-2076) Recommendation of the Public Works and Services Committee on 6-8-10: That Change Order No. 2 on Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor, be approved in the amount of $6,233.00. Further recommends that funding to defray the cost of this change order be appropriated from Account 990.220.5030, CHP-Structural Repairs. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 02-10 CO #2.pdf, 2. 02-10 CO #2.pdf
Related files: Res.10-2076
Title
Subject: (Direct Referral) Communication from the Assistant Commissioner of Public Works/Operations submitting Change Order No. 2 to Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor.  (Res.10-2076)
 
Recommendation of the Public Works and Services Committee on 6-8-10: That Change Order No. 2 on Contract 2-10 (K0-002), Incinerator Building Structural Slab Repair, Seater Construction Co., Inc., contractor, be approved in the amount of $6,233.00.
 
Further recommends that funding to defray the cost of this change order be appropriated from Account 990.220.5030, CHP-Structural Repairs.
 
Fiscal Note: Funds are available as herein delineated.