File #: Res.10-2308    Version: A Name: Change Order No. 1 on Contract 18-10 (K0-018), South Side Street Paving (R1), Milwaukee General Contractors, Inc., contractor, be approved
Type: Resolution Status: Passed
File created: 12/7/2010 In control: City Attorney's Office
On agenda: Final action: 12/7/2010
Title: Change Order No. 1 on Contract 18-10 (K0-018), South Side Street Paving (R1), Milwaukee General Contractors, Inc., contractor, be approved Resolved, that Change Order No. 1 on Contract 18-10 (K0-018), South Side Street Paving (R1), Milwaukee General Contractors, Inc., contractor, be approved in the amount of $27,815.06. Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts: $24,332.06 - Account 990.908.5010, Conc. Street Paving-Misc. Loc. $ 9,250.00 - Account 287.990.5310, Sanitary Sewer-Var. Loc. ($ 5,767.00) - Storm Sewer-Misc. Loc. $27,815.06 - Total FISCAL NOTE: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 10-5836
Sponsor
Alderman Helding
 
Title
Change Order No. 1 on Contract 18-10 (K0-018), South Side Street Paving (R1), Milwaukee General Contractors, Inc., contractor, be approved
 
Resolved, that Change Order No. 1 on Contract 18-10 (K0-018), South Side Street Paving (R1), Milwaukee General Contractors, Inc., contractor, be approved in the amount of $27,815.06.
 
Further resolved, that funding to defray the cost of this change order be appropriated from the following accounts:
 
$24,332.06 - Account 990.908.5010, Conc. Street Paving-Misc. Loc.
$  9,250.00 - Account 287.990.5310, Sanitary Sewer-Var. Loc.
($ 5,767.00) - Storm Sewer-Misc. Loc.
$27,815.06 - Total
 
FISCAL NOTE:  Funds are available as herein delineated.