Ricine Banner
File #: Res.09-1527    Version: A Name: Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II (R1), be awarded to AZAR, LLC
Type: Resolution Status: Passed
File created: 7/21/2009 In control: City Attorney's Office
On agenda: Final action: 7/21/2009
Title: Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II (R1), be awarded to AZAR, LLC Resolved, that Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II (R1), be awarded to AZAR, LLC, Racine, WI, at their bid price of $496,725.00, they being the lowest responsible bidder. Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts: $ 485,973.00 - Account 906.000.5520, Sidewalk Replacement $ 352.00 - Account 989.908.5530, Crosswalk Ramps $ 10,400.00 - Account 989.908.5320, Replacement Curb & Gutter $ 496,725.00 - Total Fiscal Note: Funds are available as herein delineated.
Sponsors: Gregory Helding
Related files: 09-3856
Sponsor
Alderman Helding
 
Title
Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II (R1), be awarded to AZAR, LLC
 
Resolved, that Contract 51-09 (K9-052), 2009 Sidewalk Replacement, Phase II (R1), be awarded to AZAR, LLC, Racine, WI, at their bid price of $496,725.00, they being the lowest responsible bidder.
 
Further resolved, that funding to defray the cost of this public works project be appropriated from the following accounts:
 
$ 485,973.00  - Account 906.000.5520, Sidewalk Replacement
$     352.00     - Account 989.908.5530, Crosswalk Ramps
$  10,400.00   - Account 989.908.5320, Replacement Curb & Gutter
$ 496,725.00 - Total
 
Fiscal Note: Funds are available as herein delineated.