File #: 11-6318    Version: A Name: Amendment No. 2 to Contract 03-11 (K1-003), PS - Design Services for Repairs to the Spring Street Bridge, Ayres Associates, Inc., contractor.
Type: Communication Status: Passed
File created: 4/18/2011 In control: Public Works and Services Committee
On agenda: Final action: 5/3/2011
Title: Subject: (Direct Referral) Communication from the Interim Commissioner of Public Works/City Engineer submitting Amendment No. 2 to Contract 3-11 (K1-003), Professional Services for Design Services for Repairs to the Spring Street Bridge, Ayres Associates, Inc., contractor. (Res.11-2538) Recommendation of the Public Works and Services Committee on 4-26-11: That Amendment No. 2 to Contract 3-11 (K1-003), Professional Services for Design Services for Repairs to the Spring Street Bridge, Ayres Associates, Inc., consultant, as submitted, be approved in the amount of $18,750.00. Further recommends that funding to defray the cost of these professional services be appropriated from Account 991.520.5010, Mill/Cast Overlay Spring Street Bridge. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 11-6318
Related files: Res.11-2538
Title
Subject: (Direct Referral) Communication from the Interim Commissioner of Public Works/City Engineer submitting Amendment No. 2 to Contract 3-11 (K1-003), Professional Services for Design Services for Repairs to the Spring Street Bridge, Ayres Associates, Inc., contractor.  (Res.11-2538)
 
Recommendation of the Public Works and Services Committee on 4-26-11:  That Amendment No. 2 to Contract 3-11 (K1-003), Professional Services for Design Services for Repairs to the Spring Street Bridge, Ayres Associates, Inc., consultant, as submitted, be approved in the amount of $18,750.00.
 
Further recommends that funding to defray the cost of these professional services be appropriated from Account 991.520.5010, Mill/Cast Overlay Spring Street Bridge.
 
Fiscal Note:  Funds are available as herein delineated.