Sponsor
Alderman Hart
Title
Change Order for HVAC Controls at Community Centers
Resolved, that Change Order No. 1 on Contract 44-06 (K6-047), Upgrade Temperature and HVAC Controls at Community Centers, Johnson Controls, Inc., contractor, as submitted, be approved in the amount of $3,193.00.
Further resolved, that funding to defray to cost of this change order be appropriated from Account 987.640.5010, Tyler/Domer BAS.
Fiscal Note: Funds are available as herein delineated.