File #: Res.12-2945    Version: A Name: Change Order #1 to Contract 12-11 (K1-012), Sidewalk Replacement - Phase I, Standard Sidewalk, Inc., Contractor.
Type: Resolution Status: Passed
File created: 2/7/2012 In control: City Attorney's Office
On agenda: Final action: 2/7/2012
Title: Change Order #1 to Contract 12-11 (K1-012), Sidewalk Replacement - Phase I, Standard Sidewalk, Inc., Contractor. Resolved, that Change Order No. 1 on Contract 12-11 (K1-012), Sidewalk Replacement - Phase I, Standard Sidewalk, Inc., Contractor, is approved in the decreased amount of $54,392.61. Fiscal Note: Change Order No. 1 will result in a decrease in contract price. Funding accounts to be adjusted by the following amounts: $ 71,773.11 - Account 906.000.5520, Sidewalk Replacement $ 10,000.00 - Account 991.908.5520, Sidewalk Replacement ($ 15,000.00) - Account 991.908.5310, New Curb & Gutter ($ 12,380.50) - Account 991.908.5010, Concrete St. Pav. Misc. Loc. $ 54,392.61 - Total
Sponsors: Sandy Weidner
Related files: 12-7315
Sponsor
Alderman Weidner
 
Title
Change Order #1 to Contract 12-11 (K1-012), Sidewalk Replacement - Phase I, Standard Sidewalk, Inc., Contractor.
 
Resolved, that Change Order No. 1 on Contract 12-11 (K1-012), Sidewalk Replacement - Phase I, Standard Sidewalk, Inc., Contractor, is approved in the decreased amount of $54,392.61.
 
Fiscal Note: Change Order No. 1 will result in a decrease in contract price. Funding accounts to be adjusted by the following amounts:
 
$ 71,773.11 - Account 906.000.5520, Sidewalk Replacement
$ 10,000.00 - Account 991.908.5520, Sidewalk Replacement
($ 15,000.00) - Account 991.908.5310, New Curb & Gutter
($ 12,380.50) - Account 991.908.5010, Concrete St. Pav. Misc. Loc.
$ 54,392.61 - Total