File #: 0612-16    Version: A Name: Change Order No. 2 on Contract 20150019, Lake Michigan Pathway, Phase lll, Ray Hintz, Inc., contractor. (Res No. 0278-16)
Type: Communication Status: Passed
File created: 7/13/2016 In control: Public Works and Services Committee
On agenda: Final action: 8/1/2016
Title: Subject: Change Order No. 2 on Contract 20150019, Lake Michigan Pathway, Phase lll, Ray Hintz, Inc., contractor. (Res No. 0278-16) Recommendation of the Public Works and Services Committee on 07-26-16: That Change Order No. 2 on Contract 20150019, Lake Michigan Pathway, Phase lll, Ray Hintz, Inc., contractor, as submitted, be approved in the amount of $2,550.00. Further recommends that funding to defray the cost of the change order be appropriated from the following Org-Objects: $ 510.00 - Org-Object 45040-57550, DPW-Lake MI Pathway $2,040.00 - Org-Object 2031-57550, State’s Share Lake MI Pathway $2,550.00 - Total Fiscal Note: Funds are available as herein delineated.
Attachments: 1. 0612-16 CO2 Contract 20150019 LMP Phase lll

Title

Subject: Change Order No. 2 on Contract 20150019, Lake Michigan Pathway, Phase lll, Ray Hintz, Inc., contractor. (Res No. 0278-16)

 

Recommendation of the Public Works and Services Committee on 07-26-16: That Change Order No. 2 on Contract 20150019, Lake Michigan Pathway, Phase lll, Ray Hintz, Inc., contractor, as submitted, be approved in the amount of $2,550.00.

 

Further recommends that funding to defray the cost of the change order be appropriated from the following Org-Objects:

 

$   510.00 - Org-Object 45040-57550, DPW-Lake MI Pathway

$2,040.00 - Org-Object 2031-57550, State’s Share Lake MI Pathway

$2,550.00 - Total

 