Title
Subject: (Direct Referral) Change Order No. 1 to Contract 20160015, 2016 Concrete Reconstruction - Kinzie Avenue (R1), Cornerstone Pavers, LLC., contractor. (Res No. 0097-17)
Recommendation of the Public Works and Services Committee on 02-28-17: Defer
Recommendation of the Public Works and Services Committee on 03-14-17: That Change Order No. 1 on Contract 20160015, 2016 Concrete Reconstruction - Kinzie Avenue (R1), Cornerstone Pavers, LLC., contractor, as submitted, be approved in the deduct amount of ($66,880.97).
Further recommends that the funding accounts be adjusted by the following amount:
($50,737.70) - Org-Object 45040-57500, DPW-Paving
$ 309.40 - Org-Object 45040-57515, DPW-Sidewalks
$ 96.26 - Org-Object 60484-57570, Storm Sewers
($23,761.28) - Org-Object 22640-57560, Sanitary Sewers
$ 2,510.49 - Org-Object 40102-57500, W/W Project-Water Main
$ 4,701.86 - Org-Object 40102-57560, W/W Project-Sanitary Sewer
($66,880.97) - Total
Fiscal Note: Funds are available as herein delineated.