Resolved, that Change Order No. 1 on Contract 20160040, 2016 Sewer Main and Lateral Lining, Musson Brothers, contractor, as submitted, is approved in the deduct amount of $229,000.50.
Fiscal Note: Funding accounts be adjusted by the following amounts:
($182,773.25) - Org-Object 40102-57560, Sanitary Sewers-RWWU Surcharge Fund
($ 46,227.25) - Org-Object 22640-57560, Sanitary Sewer
($229,000.50) - Total
|
Sponsor
Alderman McCarthy
Title
Change Order No. 1 on Contract 20160040, 2016 Sewer Main and Lateral Lining, Musson Brothers, Contractor
Resolved, that Change Order No. 1 on Contract 20160040, 2016 Sewer Main and Lateral Lining, Musson Brothers, contractor, as submitted, is approved in the deduct amount of $229,000.50.
Fiscal Note: Funding accounts be adjusted by the following amounts:
($182,773.25) - Org-Object 40102-57560, Sanitary Sewers-RWWU Surcharge Fund
($ 46,227.25) - Org-Object 22640-57560, Sanitary Sewer