Final Payment on Contract 20160040, 2016 Sanitary, Storm, and Interceptor Sewer Lining
Resolved, that the work done by Musson Brothers, under Contract 20160040, 2016 Sanitary, Storm, and Interceptor Sewer Lining, is accepted, and final payment authorized for a total contract amount of $1,149,073.15.