File #: 0069-18    Version: A Name: Subject: (Direct Referral) Communication from the Director of Parks, Recreation & Cultural Services requesting Change Order No. 1 for Contract 20170013, Gaslight Pointe Walkway Repairs - RAZA of Racine, LLC, contractor. (Res. 0019-18)
Type: Communication Status: Passed
File created: 1/18/2018 In control: Public Works and Services Committee
On agenda: Final action: 2/6/2018
Title: Subject: (Direct Referral) Communication from the Director of Parks, Recreation & Cultural Services requesting Change Order No. 1 for Contract 20170013, Gaslight Pointe Walkway Repairs, RAZA of Racine, LLC, contractor. (Res. 0019-18) Recommendation of the Public Works and Services Committee on 01-30-18: That Change Order No. 1 on Contract 20170013, Gaslight Pointe Walkway Repairs, RAZA of Racine, LLC., contractor, be approved in the amount of $2,477.00. Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 45050-57515, Parks Sidewalks. Fiscal Note: Funds are available as herein delineated.
Attachments: 1. Approved CO 1 - Gaslighte handicap Ramp 10172017 RTR, 2. Communication Change Order 1 Contract 20170013 Gaslight Walkway Repairs_PublicWorksServices, 3. Contract Change Order 1- 20170013
Related files: Res.0019-18

Title

Subject: (Direct Referral) Communication from the Director of Parks, Recreation & Cultural Services requesting Change Order No. 1 for Contract 20170013, Gaslight Pointe Walkway Repairs, RAZA of Racine, LLC, contractor. (Res. 0019-18)

 

Recommendation of the Public Works and Services Committee on 01-30-18: That Change Order No. 1 on Contract 20170013, Gaslight Pointe Walkway Repairs, RAZA of Racine, LLC., contractor, be approved in the amount of $2,477.00.

 

Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 45050-57515, Parks Sidewalks.

 

Fiscal Note:  Funds are available as herein delineated.