File #: 0419-18    Version: A Name: Change Order No. 1 on Contract 20170095, Main St. Lift Bridge - Electrical Updates, MP Systems, Inc., contractor. (Res. 0140-18)
Type: Communication Status: Passed
File created: 4/20/2018 In control: Public Works and Services Committee
On agenda: Final action: 5/1/2018
Title: Subject: (Direct Referral) Change Order No. 1 on Contract 20170095, Main St. Lift Bridge - Electrical Updates, MP Systems, Inc., contractor. (Res. 0140-18) Recommendation of the Public Works and Services Committee on 04-24-18: That Change Order No. 1 on Contract 20170095, Main St. Lift Bridge - Electrical Upgrades, MP Systems, Inc., contractor, as submitted, be approved in the amount of $4,553.00. Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 40402-57545, Main St. Lift Bridge. Fiscal Note: Funds are available as herein delineated and will be fully reimbursed by the State.
Attachments: 1. 0419-18 CO1 Contract 20170095, Main St. Lift Bridge - Electrical Updates.pdf
Related files: Res.0140-18

Title

Subject: (Direct Referral) Change Order No. 1 on Contract 20170095, Main St. Lift Bridge - Electrical Updates, MP Systems, Inc., contractor. (Res. 0140-18)

 

Recommendation of the Public Works and Services Committee on 04-24-18: That Change Order No. 1 on Contract 20170095, Main St. Lift Bridge - Electrical Upgrades, MP Systems, Inc., contractor, as submitted, be approved in the amount of $4,553.00.

 

Further recommends that funding to defray the cost of the change order be appropriated from Org-Object 40402-57545, Main St. Lift Bridge.

 

Fiscal Note:  Funds are available as herein delineated and will be fully reimbursed by the State.