Title:
|
Subject: Communication sponsored by Alder Land, on behalf of the Interim City Engineer, submitting Change Order No. 2 on Contract 20200009 - 21st Street Concrete Reconstruct - Contractor: Zignego Group, Inc.
Recommendation of the Public Works and Service Committee on 12-8-20: That Change Order No. 2 on Contract 20200009 - 21st Street Concrete Reconstruct, Zignego Group, Inc. be approved in the amount of $95,939.67.
Fiscal Note: Funding to cover the cost of this change order is available in Org-Obj 45040 57500, Concrete Street Paving, Misc. Locations.
|