12-7602
| A | 3. | March 2012 Budget Expenditures | Communication | Subject: Budget Expenditures for March 2012 Totaling $1,410,167.58
Recommendation: Approve | Approved | Pass |
Action details
|
Not available
|
12-7599
| A | 4. | Project Reports | Communication | Subject: Project Reports:
A) Update on 2011 Audit
B) Water Main Construction Updates
C) Update on Plant Pumping
D) 11th Street Change Order - CDBG Funding
E) Caledonia Water Agreement
F) SEDA Fire Flow Test
G) New Employees
Recommendation: Receive and File | Received and Filed | |
Action details
|
Not available
|
12-7600
| A | 5. | Contract W-12-7 Bid Opening Results | Communication | Subject: Bid Opening Results on Contract W-12-7, 2012 Pavement Restoration
Recommendation: Approve | Approved | Pass |
Action details
|
Not available
|
12-7601
| A | 6. | Contract W-11-6 - CO #1 | Communication | Subject: Change Order No. 1 on Contract W-11-6, Filter Wash Water Pumps VFD Replacement, Rawson Contractors, Inc. (Contractor)
Recommendation: Approve | Approved | Pass |
Action details
|
Not available
|
12-7627
| A | 7. | 2004 Bond Issue Refinancing (Res. 12-3155) | Communication | Subject: Approval of Refinancing 2004 Bond Issue (Res. 12-3155)
Recommendation of the Racine Waterworks Commission on 4/24/12: To approve.
FURTHER RECOMMEND, THE ITEM BE REFERRED TO THE FINANCE AND PERSONNEL COMMITTEE
Recommendation of the Finance & Personnel Committee on 5-21-12: To approve refinancing the 2004 Water Utility Revenue Bond Issue.
Fiscal Note: The Water Utility could save $724,000.00 by refinancing this bond. | Recommended For Approval | Pass |
Action details
|
Not available
|