07-0767
| A | 3. | May 2007 Budget Expenditures | Communication | Subject: Budget expenditures for May 2007 totaling $1,331,077.33
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0768
| A | 4. | Project Reports | Communication | Subject: Project Reports
A. Consumer Confidence Report (CCR) - Keith Haas
B. Lead Service Study - Keith Haas
C. Public Service Commission Rate Case - Ken Scolaro
D. Construction Projects - Chad Regalia
Recommendation: Receive and File | Received and Filed | |
Action details
|
Not available
|
07-0782
| A | 5. | 2006 Audit Presentation | Communication | Subject: Communication from the General Manager of the Water Utility presenting the 2006 audit from Clifton-Gunderson.
Recommendation of the Finance & Personnel Committee on 7-9-07: Receive and file the 2006 audited Water utility financial statements.
Fiscal Note: The 2006 Water utility financial statements will be merged into the 2006 City of Racine financial statements. | Recommended For Adoption | |
Action details
|
Not available
|
07-0841
| A | 6. | Bid Opening - Contract W-07-5 | Communication | Subject: Bid Opening on Contract W-07-5, Durand Avenue Water Main Alteration
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0769
| A | 7. | CO #10 - Contract W-05-8 | Communication | Subject: Change Order No. 10 on Contract W-05-8, Newman Road Water Booster Station, Riley Construction Company, Inc. (Contractor)
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0774
| A | 8. | CO #11 - Contract W-05-8 | Communication | Subject: Change Order No. 11 on Contract W-05-8, Newman Road Water Booster Station, Riley Construction Company, Inc. (contractor)
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0813
| A | 9. | CO #12 - Contract W-05-8 | Communication | Subject: Change Order No. 12 on Contract W-05-8, Newman Road Water Booster Station, Riley Construction Company, Inc. (contractor)
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0778
| A | 10. | Contract W-05-5 Final Payment | Communication | Subject: Request for final payment on Contract W-05-5, 2005 Cathodic Protection Installation - 16" & 24" Water Mains, Willkomm Excavating & Grading, Inc. (contractor)
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0787
| A | 11. | Electrical Systems Proposal | Communication | Subject: Professional services proposal from Electrical Systems regarding Perry Avenue transformer
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0805
| A | 12. | 6th St. Water Main | Communication | Subject: Water Main - 700 Block of Sixth Street
Recommendation: Approve | Approved | |
Action details
|
Not available
|
07-0818
| A | 13. | Use of City property for temp spoils storage | Communication | Subject: Communication from the General Manager requesting use of City property for temporary spoils storage.
Recommendation of the City Plan Commission on 8-8-07: That a request from the General Manager of the Water and Waste Water Utilities, seeking to use City property at 710 Rickeman Ct. for temporary storage of spoils from water main breaks be approved, subject to the following conditions:
a. That the plans presented to the Plan Commission on August 8, 2007 be approved subject to the conditions contained herein.
b. That this facility comply with hydrologic standards outlined in Section 114-851 of the Zoning Ordinance of the City and all other applicable regulations of Section 114 relating to activities in floodland and shoreland areas.
c. That all applicable permits be obtained from the Building Inspection Department.
d. That no minor changes be made from the conditions of this approval without the approval of the Plan Commission and no major changes be made from the conditions of this permit without the approval of the Common Council.
e. That this approval is | Recommended For Further Consideration | |
Action details
|
Not available
|