0533-25
| A | | Subject: Approval of Minutes for the April 16, 2025, Waterworks Commission Meeting
Staff Recommendation: To Approve
Fiscal Note: N/A | Communication | Subject: Approval of Minutes for the April 16, 2025, Waterworks Commission Meeting
Staff Recommendation: To Approve
Fiscal Note: N/A | Approved | Pass |
Action details
|
Not available
|
|
0534-25
| B | | Subject: Communication from the Utility Director Regarding 2024 Consumer Confidence Report (CCR)
https://cityofracine.org/wp-content/uploads/2025/04/2024-RWU-CCR-1.pdf
Staff Recommendation: To Receive and File
Fiscal Note: N/A | Communication | Subject: Communication from the Utility Director Regarding 2024 Consumer Confidence Report (CCR)
https://cityofracine.org/wp-content/uploads/2025/04/2024-RWU-CCR-1.pdf
Staff Recommendation: To Receive and File
Fiscal Note: N/A | Received and Filed | Pass |
Action details
|
Not available
|
|
0535-25
| B | | Subject: Communication from the Utility Director Regarding the 2024 Wisconsin Waterworks Excellence Project (WWEP)
https://mannyteodoro.com/wwep-report-cards/
Staff Recommendation: To Receive and File
Fiscal Note: N/A | Communication | Subject: Communication from the Utility Director Regarding the 2024 Wisconsin Waterworks Excellence Project (WWEP)
https://mannyteodoro.com/wwep-report-cards/
Staff Recommendation: To Receive and File
Fiscal Note: N/A | Received and Filed | Pass |
Action details
|
Not available
|
|
0536-25
| A | | Subject: Consideration of the Comprehensive Plan for Replacement of all Lead Service Lines by CDM Smith
Staff Recommendation: To Approve
Fiscal Note: N/A | Communication | Subject: Consideration of the Comprehensive Plan for Replacement of all Lead Service Lines by CDM Smith
Staff Recommendation: To Approve
Fiscal Note: N/A | Approved | Pass |
Action details
|
Not available
|
|
0541-25
| A | | Subject: Consideration of Bid Opening Results on Contract W-25-8, 2025 42" Transmission Water Main - Phase 4
Staff Recommendation: To Approve
Fiscal Note: Lowest responsive bid from A.W. Oakes & Son, Inc. at $9,374,674.00. | Communication | Subject: Consideration of Bid Opening Results on Contract W-25-8, 2025 42" Transmission Water Main - Phase 4
Staff Recommendation: To Approve
Fiscal Note: Lowest responsive bid from A.W. Oakes & Son, Inc. at $9,374,674.00. | Approved | Pass |
Action details
|
Not available
|
|
0542-25
| A | | Subject: Consideration of Bid Opening Results on Contract W-25-9, 2025 Water Main Replacement - Phase 3
Staff Recommendation: To Approve
Fiscal Note: Lowest responsive bid from Willkomm Excavating & Grading, Inc.at 486,070.00. | Communication | Subject: Consideration of Bid Opening Results on Contract W-25-9, 2025 Water Main Replacement - Phase 3
Staff Recommendation: To Approve
Fiscal Note: Lowest responsive bid from Willkomm Excavating & Grading, Inc.at 486,070.00. | Approved | Pass |
Action details
|
Not available
|
|
0544-25
| A | | Subject: Change Order No. 1 on Contract W-23-7, 42" Water Main Phase 3 Project, Super Excavators, Inc. (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract Change results in an increase of $19,020.00, bringing the total contract amoun | Communication | Subject: Change Order No. 1 on Contract W-23-7, 42" Water Main Phase 3 Project, Super Excavators, Inc. (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract Change results in an increase of $19,020.00, bringing the total contract amount to $18,220,360.00. | Approved | Pass |
Action details
|
Not available
|