Ricine Banner
File #: 0006-25    Version: A Name: Subject: Consideration of Change Order #1, Contract 2024-WW-STR-01 - 2024 Racine Wastewater Treatment Plant Roof Replacements, Carlson Racine Roofing & Sheet Metal Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change resul
Type: Communication Status: In Committee
File created: 1/3/2025 In control: Wastewater Commission
On agenda: Final action:
Title: Subject: Consideration of Change Order #1, Contract 2024-WW-STR-01 - 2024 Racine Wastewater Treatment Plant Roof Replacements, Carlson Racine Roofing & Sheet Metal Inc. (contractor) Staff Recommendation: To Approve Fiscal Note: Contract change results in a decrease of $4,987.00, bringing the total contract amount to $259,968.00.
Attachments: 1. co#1_contract 2024-WW-STR-01
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Subject: Consideration of Change Order #1, Contract 2024-WW-STR-01 - 2024 Racine Wastewater Treatment Plant Roof Replacements, Carlson Racine Roofing & Sheet Metal Inc. (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Contract change results in a decrease of $4,987.00, bringing the total contract amount to $259,968.00.