File #: 09-3718    Version: A Name: CO #1 - Contract C-08
Type: Communication Status: Passed
File created: 6/3/2009 In control: Wastewater Commission
On agenda: Final action: 6/30/2009
Title: Subject: Change Order No. 1 on Contract C-08, Lift Station No. 2 Force Main Replacement, G. B. Johnson, Inc. (Contractor) Recommendation: Approve
Title
Subject: Change Order No. 1 on Contract C-08, Lift Station No. 2 Force Main Replacement, G. B. Johnson, Inc. (Contractor)
 