File #: 0908-23    Version: A Name: Subject: Approval of Change Order No. 1 on Contract D-22 Biogas Conditioning Project, Lee Mechanical (contractor) Recommendation: To Approve Fiscal Note: Contract change results in an increase of $53,035.96, bringing the contract amount to $1,906,03
Type: Communication Status: Passed
File created: 9/13/2023 In control: Wastewater Commission
On agenda: Final action: 9/19/2023
Title: Subject: Approval of Change Order No. 1 on Contract D-22 Biogas Conditioning Project, Lee Mechanical (contractor) Recommendation: To Approve Fiscal Note: Contract change results in an increase of $53,035.96, bringing the contract amount to $1,906,035.96. This change order reflects an increase of 2.9% on the original contract amount.
Attachments: 1. D-22_biogas conditioning_co#1

Title

Subject: Approval of Change Order No. 1 on Contract D-22 Biogas Conditioning Project, Lee Mechanical (contractor)

 

Recommendation: To Approve

 

Fiscal Note: Contract change results in an increase of $53,035.96, bringing the contract amount to $1,906,035.96. This change order reflects an increase of 2.9% on the original contract amount.