Ricine Banner
File #: 1004-24    Version: A Name: Subject: Change Order #3 on Contract D-22 - Biogas Conditioning, Lee Mechanical (contractor) Staff Recommendation: To Approve Fiscal Note: Zero dollar change order to extend substantial and final completion dates.
Type: Communication Status: Passed
File created: 11/6/2024 In control: Wastewater Commission
On agenda: Final action: 11/20/2024
Title: Subject: Change Order #3 on Contract D-22 - Biogas Conditioning, Lee Mechanical (contractor) Staff Recommendation: To Approve Fiscal Note: Zero dollar change order to extend substantial and final completion dates.
Attachments: 1. co#3_contract D-22_biogas conditioning

Title

Subject: Change Order #3 on Contract D-22 - Biogas Conditioning, Lee Mechanical (contractor)

 

Staff Recommendation: To Approve

 

Fiscal Note: Zero dollar change order to extend substantial and final completion dates.