0027-26
| A | | Subject: Approval of Minutes for the November 19, 2025, Wastewater Commission Meeting
Staff Recommendation: To Approve
Fiscal Note: N/A | Communication | Subject: Approval of Minutes for the November 19, 2025, Wastewater Commission Meeting
Staff Recommendation: To Approve
Fiscal Note: N/A | | |
Not available
|
Not available
|
|
0063-26
| A | | Subject: Consideration of Amendments to the Industrial Pretreatment Enforcement Response Plan
Staff Recommendation: To Approve
Fiscal Note: N/A | Communication | Subject: Consideration of Amendments to the Industrial Pretreatment Enforcement Response Plan
Staff Recommendation: To Approve
Fiscal Note: N/A | | |
Not available
|
Not available
|
|
0028-26
| A | | Subject: Communication from City Finance and City Customer Service Departments Regarding Utility Administrative Changes
Staff Recommendation: To Receive and File
Fiscal Note: N/A | Communication | Subject: Communication from City Finance and City Customer Service Departments Regarding Utility Administrative Changes
Staff Recommendation: To Receive and File
Fiscal Note: N/A | | |
Not available
|
Not available
|
|
0065-26
| A | | | Communication | Subject: Consideration of Professional Services Agreement with Carollo for Plant-Wide HVAC Study
Staff Recommendation: To Approve
Fiscal Note: Cost not to exceed amount of $147,878 from Professional Services Budget. | | |
Not available
|
Not available
|
|
0030-26
| A | | Subject: Communication from Wastewater Utility Staff Regarding Treatment Plant and Conveyance System Project Updates
Staff Recommendation: To Receive and File
Fiscal Note: N/A | Communication | Subject: Communication from Wastewater Utility Staff Regarding Treatment Plant and Conveyance System Project Updates
Staff Recommendation: To Receive and File
Fiscal Note: N/A | | |
Not available
|
Not available
|
|
0064-26
| A | | Subject: Consideration of Change Order No. 2 - Contract A-23, Chicory Road Area Sewer Improvements - Miron Construction (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in a decrease of $29,892.51 bringing the total | Communication | Subject: Consideration of Change Order No. 2 - Contract A-23, Chicory Road Area Sewer Improvements - Miron Construction (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in a decrease of $29,892.51 bringing the total contract amount to $10,258,315.89. | | |
Not available
|
Not available
|
|
0034-26
| A | | Subject: Consideration of Change Order No. 3 on Contract C-22 - Engines & Blowers Project, August Winter & Sons, Inc. (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in an increase of $252,344.00, bringing the tota | Communication | Subject: Consideration of Change Order No. 3 on Contract C-22 - Engines & Blowers Project, August Winter & Sons, Inc. (contractor)
Staff Recommendation: To Approve
Fiscal Note: Contract change results in an increase of $252,344.00, bringing the total contract amount to $6,722,257.00. | | |
Not available
|
Not available
|
|
0035-26
| A | | Subject: Consideration of Amendment #1 of Construction Engineering Contract with AECOM related to Contract C-22, Engine/Blower Project
Staff Recommendation: To Approve
Fiscal Note: Contract change results in an increase of $175,425.00 bringing the t | Communication | Subject: Consideration of Amendment #1 of Construction Engineering Contract with AECOM related to Contract C-22, Engine/Blower Project
Staff Recommendation: To Approve
Fiscal Note: Contract change results in an increase of $175,425.00 bringing the total contract amount to $1,054,525.00. | | |
Not available
|
Not available
|